Project status update

Ampoint Sanitary Sewer Replacement, Perrysburg Township — Project is underway.  Work taking place throughout Ampoint Development with construction traffic on Third and J Street and other areas.  Sanitary Sewer construction expected to be complete by end of July or early August of this year.  Traffic and service disruptions should be minimal and temporary.

Hillside Drive Sanitary Sewer and Waterline Replacement, Rossford — Installation of water lines and sanitary sewer is complete.  Residents can begin to have their contractor make connections to the sanitary sewer.  Contact NWWSD prior to starting the work.  Water services reconnected to new water line.  Trench compaction is underway and should be complete this week.  Temporary road construction will take place shortly thereafter.  Coordination with Rossford for the final replacement of the road by the City underway.  District project completed by end of July anticipated.

River Road Phase 2 Waterline Replacement, Rossford and Perrysburg Township — Project underway.  Main water line installation approximately 75% complete.  Water service reconnections and  restoration taking place in various areas where the water line has been installed and tested.  Wet weather has delayed restoration in some areas.  This work will proceed when areas are dry.  One lane closure will continue on River Road while construction is proceeding.  Occasional temporary water shutoffs will occur.  Notifications will be placed at each residence prior to shutoffs.  Work will continue for two to three months.

Colony Area Sanitary Sewer Rehabilitation, Rossford — Construction commenced last week on Riverside Drive and will continue for two to three weeks.   Traffic will be maintained.  Occasional reduced sewage usage when the contractor is installing new pipe in an area may be required, lasting for four to eight hours.   Contractor will notify residences ahead of time.   Contractor will be working in the entire neighborhood for the next four to five months.  Privately owned items within the road right of way may be damaged and should be removed ahead of time.

Hufford Road Waterline Replacement, Perrysburg Township — Replacement of existing waterline on Hufford Road between River Road and Avenue Road.  Work has begun and will continue for several months.  Local traffic will be maintained.  Occasional temporary water shutoffs will be scheduled ahead of time and notifications will be made.

Jennings Rd Pump Station, Rossford — Construction will start in early September.  Work will involve the construction of a new pump station within the park and the partial removal and abandonment of the existing pump station near the end of Jennings Road.