Rossford Construction Update

Jennings Rd Pump Station, Rossford—Construction start early September.  Work will involve the construction of a new pump station within the park and the partial removal and abandonment of the existing pump station near the end of Jennings Road.  Work is scheduled to begin after the Labor Day weekend.

 

Ampoint Sanitary Sewer Replacement, Perrysburg Township—Project underway.  Work taking place throughout Ampoint Development with construction traffic on Third and J Street and other areas.  Sanitary Sewer construction expected to be complete in August of this year.  Traffic and service disruptions should be minimal and temporary.  Restoration of streets, drives and yards will be ongoing.

 

Hillside Drive Sanitary Sewer and Waterline Replacement, Rossford--Installation of waterlines and sewer is complete.  Residents can begin to have their contractor make connections to the sanitary sewer.  Contact NWWSD prior to starting the work.  Water services reconnected to new water line.  Residents should contact Engineering at District with questions related to water system changes and sanitary sewer lateral reconnections.  Coordination with Rossford for the final replacement of the road by the City underway.  District project complete.  Final restoration to be completed after Rossford storm sewer and road work completed.

 

River Road Phase 2 Waterline Replacement, Rossford and Perrysburg Township—Project underway.  Main waterline installation approximately 80% complete.  Water services reconnections and  restoration taking place in various areas where the waterline has been installed and tested.  Wet weather has delayed restoration in some areas.  A significant portion of the restoration has been completed.  One lane closure will continue on River Road while construction is proceeding.  Residents are encouraged to carefully exits drives and during travel through the construction zone.  Occasional temporary water shutoffs will occur.  Notifications will be placed at each residence prior to shutoffs.  Work will continue for two months or more.

 

Colony Area Sanitary Sewer Rehabilitation, Rossford—Construction commenced on Riverside Drive and continues for the next few weeks.  After Riverside Drive is complete, the contractor will continue on Forest drive to Colony Drive.   Traffic will be maintained.  Occasional reduced sewage usage when the contractor is installing new pipe in an area may be required.  This should be for four to eight hours.   Contractor will notify residences ahead of time.   Contractor will be working in the entire neighborhood for the next four to five months.  Privately owned items within the road right of way may be damaged and should be removed ahead of time.  Residents should note when contractor nearing property for coordination.

 

Hufford Road Waterline Replacement, Perrysburg Township—Replacement of existing waterline on Hufford Road between River Road and Avenue Road.  Work has begun and will continue for several months.  Local traffic will be maintained.  Occasional temporary water shutoffs will be scheduled ahead of time and notifications will be made.