BOWLING GREEN, Ohio, - The Northwestern Water and Sewer District (the District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky and Hancock counties.  Although many of our construction and maintenance projects are performed underground, our utility work can impact roads throughout our area.  The District will announce updates and when additional projects are under contract.  Updates and additions are highlighted in bold and underlined. 

Wood County

Hydrant Flushing – Northwood & Lake Township *NEW WORK*
Through Monday, October 9, crews will be flushing hydrants throughout the City of Northwood.  Crews may also be flushing hydrants in Lake Township.  Residents are advised to flush water from taps if water becomes discolored.  Hydrant flushing will continue through December.  For more information: /operations/water-quality/hydrant-main-line-flushing-info/

Bloomdale – Water Line Maintenance
Through October, short-term, intermittent lane restrictions are possible on Cherry Street in Bloomdale for water line maintenance.  Project complete: October. 

Bairdstown – Sanitary Sewer Work
Through September, daytime, intermittent lane restrictions are possible on SR 18 between Bushey Road and Leathers Road for sewer installation.  Traffic will be maintained by flaggers.  Through September, daytime intermittent lane restrictions and short-term closures are also possible on local streets in Bairdstown for pavement and restoration work.  Project complete: September.

Millbury – Sanitary Sewer Improvements
Through June 2018, short-term, intermittent lane restrictions are possible throughout the Village of Millbury for sewer work and manhole repairs.  Project complete: June 2018.

Northwood – Curtice Road Waterline Replacement
Through November, intermittent lane restrictions are possible on Curtice Road between Bradner Road and Reva Drive for water line replacement.  Traffic will be maintained by flaggers.  Project complete: March 2018.  

Perrysburg Township – Starbright Subdivision Water Line Project *UPDATE*
Water line work impacting Oregon and Ayers Roads, adjacent to the Starbright subdivision is now complete.  Through November, lane restrictions and closures are possible within the Starbright subdivision.  Local access will be maintained.  Project complete:  November. 

Plain Township- Gypsy Lane Sewer Maintenance*WORK COMPLETE*
Sewer maintenance work on Gypsy Lane Road, between Rudolph Road and Sand Ridge Road is now complete.

Washington Township, State Route 65 Pump Station Upgrade *UPDATE*
Through October, daytime lane restrictions are possible on State Route 65 near State Route 235 for pump station upgrade.   Traffic will be maintained by flaggers.  Project complete: October.   

For a full list of projects on and off road, please visit our website: