Project Update

Monday, October 16, 2017

FOR IMMEDIATE RELEASE

 

Northwestern Water and Sewer District Projects

BOWLING GREEN, Ohio, - The Northwestern Water and Sewer District (the District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky and Hancock counties.  Although many of our construction and maintenance projects are performed underground, our utility work can impact roads throughout our area.  The District will announce updates and when additional projects are under contract.  Updates and additions are highlighted in bold and underlined. 

Wood County

Bloomdale – Water Line Maintenance
Through October, short-term, intermittent lane restrictions are possible on Cherry Street in Bloomdale for water line maintenance.  Project complete: October. 

Bairdstown – Sanitary Sewer Work *PROJECT COMPLETE*
Sewer work on SR 18 between Bushey Road and Leathers Road is complete.  Pavement and restoration work on local streets in Bairdstown is now complete.

Millbury – Sanitary Sewer Improvements
Through June 2018, short-term, intermittent lane restrictions are possible throughout the Village of Millbury for sewer work and manhole repairs.  Project complete: June 2018.

Northwood – Curtice Road Waterline Replacement
Through November, intermittent lane restrictions are possible on Curtice Road between Bradner Road and Reva Drive for minor restoration work.  Traffic will be maintained by flaggers.  Project complete: March 2018.  

Perrysburg Township – Starbright Subdivision Water Line Project
Through November, lane restrictions and closures are possible within the Starbright subdivision.  Local access will be maintained.  Project complete:  November. 

Plain Township – U.S. Route 6 – Water Main Maintenance *NEW WORK*
Effective today, through Friday, October 20, daily from 7:30am through 4pm, intermittent shoulder restrictions are possible on US 6, between Green Road and Potter Road water for main maintenance. 

Washington Township, State Route 65 Pump Station Upgrade
Through October,daytime lane restrictions are possible on State Route 65 near State Route 235 for pump station upgrade.   Traffic will be maintained by flaggers.  Project complete: October. 

Hydrant Flushing
Effective today, through December, weekdays from 8am until 3:30pm, crews will be flushing and testing fire hydrants in Northern Wood County.  Testing will be performed on all hydrants in the City of Rossford and all hydrants east of the City of Perrysburg corporation limits to I-280 in Lake Township.  The affected areas include Ampoint Industrial Park, Owens Community College, Village of Walbridge, Moline and Ohio Turnpike Exit 5 Interchange.  Subdivisions that will be tested include The Hamlet, Belmont County Club, Starbright, Lakemont, Homecraft, etc.  Residents are advised to flush water from their taps if the water becomes discolored.  For more information: /operations/water-quality/hydrant-main-line-flushing-info/

For a full list of projects on and off road, please visit our website:
/engineering/project-information/current-projects/

###

Our goal is to be the premier water and wastewater provider in Northwestern Ohio. We are committed to sound financial management, responsible environmental stewardship, responsive public service, superior customer service, and responsible economic growth.  We strive to field a skilled, respectful, and cooperative workforce dedicated to the highest professional and ethical standards; we support them with appropriate training and technology.

Theresa Pollick, Office: 419.354.9090 X 139, Cell: 419.806.1018; Email: tpollick@nwwsd.org