Project Update

Northwestern Water and Sewer District Projects

BOWLING GREEN, Ohio, - The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky, and Hancock counties.  Although many of our construction and maintenance projects are performed underground, our utility work can impact roads throughout our area.  The District will announce updates and when additional projects are under contract.  Updates and additions are highlighted in bold and underlined. 

Lake Township – Pump Station Improvements
Effective Today through April, intermittent lane restrictions are possible on Cummings Road between SR 795 and Hanley Road for pump station work.  Project complete: May.

McComb: Waterline Improvements
Restoration work for waterline improvements on Todd, Scott, South and High Streets in McComb will continue through April.  Project complete: May.   

Middleton and Plain Townships – Potter Road Waterline Installation *UPDATE*
Through April, service line and restoration work will continue on Potter Road from Poe Road to Long-Judson Road with minimal impact to traffic.  Project complete: April.   

Millbury – Sanitary Sewer Improvements
Through June, short-term, intermittent lane restrictions are possible throughout the Village of Millbury for sewer work and manhole repairs.  Project complete: June.

Northwood and Perrysburg & Lake Townships – East Broadway Sewer Maintenance
Through April, lane restrictions are possible on East Broadway Street between Walbridge and Wales Roads for sewer maintenance.  Traffic will be maintained by flaggers.  Project complete: April.

Perrysburg Township – Hamlet Waterline Replacement *UPDATE*
Effective today, through August, short-term intermittent lane restrictions and closures are possible in the Hamlet subdivision for waterline installation.  Local access will be maintained.  Project complete: August.

Perrysburg Township – Sanitary Sewer Improvements *UPDATE*
Sewer work on River Road, between White Road and Rockledge Drive has been postponed and will be announced.   Through October, short-term intermittent lane restrictions are possible throughout Perrysburg Township, north of SR 795, for sewer work and manhole repair.  Project complete: October.

Rossford – Buck and Lime City Road Water Line Relocation and Improvements *UPDATE*
Work involving lane restrictions on Buck Road between I-75 and Lime City Road is now complete.  Through March, lane restrictions are possible on Lime City Road between I -75 and Marilyn Drive for waterline installation.
  Traffic will be maintained by flaggers.  Project complete: April. 

Various Townships – Water Line Installation
Through March, intermittent lane restrictions are possible on Rosendale Road, between Jerry City and Cygnet Road for waterline installation.  Project complete: March. 

Weston - Waterline Project
Through April, short-term intermittent lane restrictions are possible on Silver Street between Sugar Lane and Euler Street for waterline installation. Project complete: June.

Weston – Pump Station Project
Through March, intermittent, short-term lane restrictions are possible on Main Street, between Russ Street and Weston Road for pump station improvements.  Project complete:  May. 

For a full list of projects on and off road, please visit our website:
/engineering/project-information/current-projects/

###

Our goal is to be the premier water and wastewater provider in Northwestern Ohio. We are committed to sound financial management, responsible environmental stewardship, responsive public service, superior customer service, and responsible economic growth.  We strive to field a skilled, respectful, and cooperative workforce dedicated to the highest professional and ethical standards; we support them with appropriate training and technology.

Theresa Pollick, Office: 419.354.9090 X 139, Cell: 419.806.1018; Email: tpollick@nwwsd.org